KDE

NAVIGATION
CATEGORIES
REFERRENCE
LINKS
  • problem with kplato on current svn version...

    13 answers - 440 bytes - related search similar search Add To My Delicious Add To My Stumble Upon Add To My Google Mark Add To My Facebook Add To My Digg Add To My Reddit

    Hi,
    I've just compiled/install the full koffice project, and kplato doesn't start.
    the app.start() returns false, that is all I can say :-/
    I compile/run it on a x86-64, and other parts of koffice are working fine.
    Is the current svn broken?
    Is it supposed to work?
    May I enable debug logs (how?)
    Thanks in advance
    Fred
    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.1 | | 631 bytes | |

    Thursday 15 December 2005 20:47, Fred Marmond wrote:
    Hi,
    I've just compiled/install the full koffice project, and kplato doesn't
    start. the app.start() returns false, that is all I can say :-/

    I compile/run it on a x86-64, and other parts of koffice are working
    fine.

    Is the current svn broken?
    Is it supposed to work?
    May I enable debug logs (how?)

    Thanks in advance

    I don't have an answer to the above question, but I want to apologize for
    the long delay for the moderator approval, I have been out of town for
    some days.
    Do you still see the above problems?
  • No.2 | | 1107 bytes | |

    Hi,
    it works fine with today's svn (it may have worked for few past days too as I
    couldn't test it until now).

    I'll play with kplato now.
    Is the actual state can be tested, or is it known to be so unstable that bug
    reporting is not welcome for now?
    Is there any place to report bugs/features requests?

    Fred

    Le Lundi 19 D 2005 22:53, Thomas Zander a *:
    Thursday 15 December 2005 20:47, Fred Marmond wrote:
    Hi,
    I've just compiled/install the full koffice project, and kplato doesn't
    start. the app.start() returns false, that is all I can say :-/

    I compile/run it on a x86-64, and other parts of koffice are working
    fine.

    Is the current svn broken?
    Is it supposed to work?
    May I enable debug logs (how?)

    Thanks in advance

    I don't have an answer to the above question, but I want to apologize for
    the long delay for the moderator approval, I have been out of town for
    some days.
    Do you still see the above problems?

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.3 | | 2292 bytes | |

    21 december 2005 13:10, fmdp wrote:
    Hi,
    it works fine with today's svn (it may have worked for few past
    days too as I couldn't test it until now).
    Good :)

    I'll play with kplato now.
    Is the actual state can be tested, or is it known to be so unstable
    that bug reporting is not welcome for now?
    Is there any place to report bugs/features requests?
    No, you can test, I don't know of any crashes atm ;)
    It's early days yet, what I try to cover for this first 0.x release is
    basic project planning. In short you can define tasks, resources,
    calendars and accounts, link tasks, assign resources to tasks and
    schedule the project.
    Finding out how to link tasks can be tricky, but if you in ganttview
    point to a task, press LMB and drag to another task, you'll get a
    link. Double clicking on a link will get you a link dialog. (I've
    plans to find a better way, suggestions wellcome)

    The ui is generally not much good, I think, but I didn't plan to do
    anything about it until qt4. Now, qt4 seems a very long time off,
    so
    But suggestions are very wellcome anyway!

    Bugs can be reported using the help menu as normal, or directly using
    bugs.kde.org, but discussing on this list first maybe better until we
    release.

    Unfortunately (?:) I'm taking a real long Christmas holiday this year,
    leaving tomorrow, not back until next year! (probably jan 3.)

    So, Merry Christmas and a Happy New Year to you all!

    Fred

    Le Lundi 19 D 2005 22:53, Thomas Zander a *:
    Thursday 15 December 2005 20:47, Fred Marmond wrote:
    Hi,
    I've just compiled/install the full koffice project, and kplato
    doesn't start. the app.start() returns false, that is all I can
    say :-/

    I compile/run it on a x86-64, and other parts of koffice are
    working fine.

    Is the current svn broken?
    Is it supposed to work?
    May I enable debug logs (how?)

    Thanks in advance

    I don't have an answer to the above question, but I want to
    apologize for the long delay for the moderator approval, I have
    been out of town for some days.
    Do you still see the above problems?

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.4 | | 4492 bytes | |

    Hi Dag,

    I play with kplato, and here are few comments:
    problems:
    - doesn't handle correctly the task duration when set more than one working
    plage per day (set 13:0->15:0 and 20:0->23:59)=all tasks are displayed as
    '1 day long' in the gantt
    - can't set ressources calendar (poor workers that can't take holidays! ;) )
    - project calendar: when days are tagged 'non worked', it doesn't alter the
    gantt

    wishes:
    - a link to Karm, to help feeding kplato with real worked times on tasks
    - can assign a ressource for a 'mother task', that will assign this ressource
    to all children's taskes
    - calculate the right start time when 'ASAP' is selected with previous effort
    sum:
    task1 (effort 2days) and task2 (effort 1d) assigned to Ressource1 and both
    start the 2005-12-21 in parrallel
    task3 (start ASAP as task1 and task2 are finished)
    Now, I see that task3 start only 2 days after task1, but Ressource1 can't work
    3 days (task1+task2) in 2 days! So, I would guess that task3 will start 'as
    soon as possible', that's to say 'as soon as Ressource1 is free', so, when he
    will have done task1+task2 =3 days after the start of task1/task2
    - add a TD set of tasks that are not yet plannified. We know that we'll have
    to work on theses tasks, and they are yet ready to be planned (we can
    annotate them, estimate effort, )
    - handle euros too (only dollars for now) (minor for now! ;) )
    - a per ressource list of tasks, in a calendar (as

    But it seems to be promising, and I hope I will be able to use it 'for real'
    soon! ;)
    The gui is not too hard to use (I miss some things like double click on task
    on gantt to edit it, or things like that) but I found the way of linking them
    alone. I used Qt4 in an other project, and yes, you are right to wait qt4 on
    kde to implement that sort of things ;)

    have nice holidays, and see you next year!

    Fred

    Le Mercredi 21 D 2005 13:44, Dag Andersen a *:
    21 december 2005 13:10, fmdp wrote:
    Hi,
    it works fine with today's svn (it may have worked for few past
    days too as I couldn't test it until now).

    Good :)

    I'll play with kplato now.
    Is the actual state can be tested, or is it known to be so unstable
    that bug reporting is not welcome for now?
    Is there any place to report bugs/features requests?

    No, you can test, I don't know of any crashes atm ;)
    It's early days yet, what I try to cover for this first 0.x release is
    basic project planning. In short you can define tasks, resources,
    calendars and accounts, link tasks, assign resources to tasks and
    schedule the project.
    Finding out how to link tasks can be tricky, but if you in ganttview
    point to a task, press LMB and drag to another task, you'll get a
    link. Double clicking on a link will get you a link dialog. (I've
    plans to find a better way, suggestions wellcome)

    The ui is generally not much good, I think, but I didn't plan to do
    anything about it until qt4. Now, qt4 seems a very long time off,
    so
    But suggestions are very wellcome anyway!

    Bugs can be reported using the help menu as normal, or directly using
    bugs.kde.org, but discussing on this list first maybe better until we
    release.

    Unfortunately (?:) I'm taking a real long Christmas holiday this year,
    leaving tomorrow, not back until next year! (probably jan 3.)

    So, Merry Christmas and a Happy New Year to you all!

    Fred

    Le Lundi 19 D 2005 22:53, Thomas Zander a *:
    Thursday 15 December 2005 20:47, Fred Marmond wrote:
    Hi,
    I've just compiled/install the full koffice project, and kplato
    doesn't start. the app.start() returns false, that is all I can
    say :-/

    I compile/run it on a x86-64, and other parts of koffice are
    working fine.

    Is the current svn broken?
    Is it supposed to work?
    May I enable debug logs (how?)

    Thanks in advance

    I don't have an answer to the above question, but I want to
    apologize for the long delay for the moderator approval, I have
    been out of town for some days.
    Do you still see the above problems?

    kplato mailing list
    kplato (AT) kde (DOT) org

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.5 | | 5039 bytes | |

    21 december 2005 14:17, fmdp wrote:
    Hi Dag,

    I play with kplato, and here are few comments:
    problems:
    - doesn't handle correctly the task duration when set more than one
    working plage per day (set 13:0->15:0 and 20:0->23:59)=all tasks
    are displayed as '1 day long' in the gantt
    I don't know what you expected to see , but it should display the task
    as starting 13:0 and ending 23:59. It doesn't show that no work is
    going on from 15:0 to 20:0.
    - can't set ressources calendar (poor workers that can't take
    holidays! ;) ) - project calendar: when days are tagged 'non
    worked', it doesn't alter the gantt
    The gantt chart doesn't (atm) display non-working days as you have set
    them in the calendar. It indicates "week-ends" as gray in accordance
    with you locale settings (I think), but this only works "correctly"
    when you have a 1 day scale.

    wishes:
    I'll come back to this, no resource leveling is implemented yet, it
    will just overbook.
    - a link to Karm, to help feeding kplato with real worked times on
    tasks - can assign a ressource for a 'mother task', that will
    assign this ressource to all children's taskes
    - calculate the right start time when 'ASAP' is selected with
    previous effort sum:
    task1 (effort 2days) and task2 (effort 1d) assigned to Ressource1
    and both start the 2005-12-21 in parrallel
    task3 (start ASAP as task1 and task2 are finished)
    Now, I see that task3 start only 2 days after task1, but Ressource1
    can't work 3 days (task1+task2) in 2 days! So, I would guess that
    task3 will start 'as soon as possible', that's to say 'as soon as
    Ressource1 is free', so, when he will have done task1+task2 =3
    days after the start of task1/task2 - add a TD set of tasks that
    are not yet plannified. We know that we'll have to work on theses
    tasks, and they are yet ready to be planned (we can annotate them,
    estimate effort, )
    - handle euros too (only dollars for now) (minor for now! ;) )
    - a per ressource list of tasks, in a calendar (as

    But it seems to be promising, and I hope I will be able to use it
    'for real' soon! ;)
    The gui is not too hard to use (I miss some things like double
    click on task on gantt to edit it, or things like that) but I found
    the way of linking them alone. I used Qt4 in an other project, and
    yes, you are right to wait qt4 on kde to implement that sort of
    things ;)

    have nice holidays, and see you next year!
    Thanks, the same to to you.

    Fred

    Le Mercredi 21 D 2005 13:44, Dag Andersen a *:
    21 december 2005 13:10, fmdp wrote:
    Hi,
    it works fine with today's svn (it may have worked for few past
    days too as I couldn't test it until now).

    Good :)

    I'll play with kplato now.
    Is the actual state can be tested, or is it known to be so
    unstable that bug reporting is not welcome for now?
    Is there any place to report bugs/features requests?

    No, you can test, I don't know of any crashes atm ;)
    It's early days yet, what I try to cover for this first 0.x
    release is basic project planning. In short you can define tasks,
    resources, calendars and accounts, link tasks, assign resources
    to tasks and schedule the project.
    Finding out how to link tasks can be tricky, but if you in
    ganttview point to a task, press LMB and drag to another task,
    you'll get a link. Double clicking on a link will get you a link
    dialog. (I've plans to find a better way, suggestions wellcome)

    The ui is generally not much good, I think, but I didn't plan to
    do anything about it until qt4. Now, qt4 seems a very long time
    off, so
    But suggestions are very wellcome anyway!

    Bugs can be reported using the help menu as normal, or directly
    using bugs.kde.org, but discussing on this list first maybe
    better until we release.

    Unfortunately (?:) I'm taking a real long Christmas holiday this
    year, leaving tomorrow, not back until next year! (probably jan
    3.)

    So, Merry Christmas and a Happy New Year to you all!

    Fred

    Le Lundi 19 D 2005 22:53, Thomas Zander a *:
    Thursday 15 December 2005 20:47, Fred Marmond wrote:
    Hi,
    I've just compiled/install the full koffice project, and
    kplato doesn't start. the app.start() returns false, that
    is all I can say :-/

    I compile/run it on a x86-64, and other parts of koffice
    are working fine.

    Is the current svn broken?
    Is it supposed to work?
    May I enable debug logs (how?)

    Thanks in advance

    I don't have an answer to the above question, but I want to
    apologize for the long delay for the moderator approval, I
    have been out of town for some days.
    Do you still see the above problems?

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.6 | | 1180 bytes | |

    Here is a testcase of the problem (see the .kplato attached)

    standard working day is 8-16 + 17-20 (11h)
    monday to friday are the same (each redefined, to be sure)
    If I create a task of 33h, it sets it to 3 days (good) but only display it in
    2 days in the gantt

    By the way, I just see an other strange thing:
    open the file I attached.
    edit one task (test2) and you'll see 'effort' of 2d 9h.
    enter something in the Note area. click ok
    Then, reedit the task, the hour area will be sub by 2! (2d 7h the very next
    time, 2d 5h, and follows like this until 2d 1h)

    Fred

    Le Mercredi 21 D 2005 14:55, Dag Andersen a *:
    21 december 2005 14:17, fmdp wrote:
    - doesn't handle correctly the task duration when set more than one
    working plage per day (set 13:0->15:0 and 20:0->23:59)=all tasks
    are displayed as '1 day long' in the gantt

    I don't know what you expected to see , but it should display the task
    as starting 13:0 and ending 23:59. It doesn't show that no work is
    going on from 15:0 to 20:0.

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.7 | | 1811 bytes | |

    21 december 2005 15:24, fmdp wrote:
    Here is a testcase of the problem (see the .kplato attached)

    standard working day is 8-16 + 17-20 (11h)
    monday to friday are the same (each redefined, to be sure)
    If I create a task of 33h, it sets it to 3 days (good) but only
    display it in 2 days in the gantt
    , think I fixed it, probably I was interrupted during implementation
    because the functionality wasn't complete. I simplified the use of
    the StandardWorktime thing (do you have a better name?). It's only
    used when entering/showing estimates now. To define working hours you
    have to use calendars. (The problem with setting calendar for
    resources is also fixes.)

    By the way, I just see an other strange thing:
    open the file I attached.
    edit one task (test2) and you'll see 'effort' of 2d 9h.
    enter something in the Note area. click ok
    Then, reedit the task, the hour area will be sub by 2! (2d 7h the
    very next time, 2d 5h, and follows like this until 2d 1h)
    Fixed. BTW, the duration/effort widget, do you you think it works ok?
    Shaheed came up with this since we wanted a (simple) way to localize
    it. It's still kind of prototype, atm it can't handle more than days,
    it should at least handle weeks imo.

    Fred

    Le Mercredi 21 D 2005 14:55, Dag Andersen a *:
    21 december 2005 14:17, fmdp wrote:
    - doesn't handle correctly the task duration when set more than
    one working plage per day (set 13:0->15:0 and 20:0->23:59)=>
    all tasks are displayed as '1 day long' in the gantt

    I don't know what you expected to see , but it should display the
    task as starting 13:0 and ending 23:59. It doesn't show that no
    work is going on from 15:0 to 20:0.
  • No.8 | | 2779 bytes | |

    Hi Dag,

    I only updated kplato and it crashes at sometimes.
    so, now, all koffice is updated & compiling and it takes long time!!!

    few answers to your questions, I'll report success/problems on the execution
    when compilation will be finished (in few hours)

    Le Mercredi 4 Janvier 2006 13:36, Dag Andersen a *:

    , think I fixed it, probably I was interrupted during implementation
    because the functionality wasn't complete. I simplified the use of
    the StandardWorktime thing (do you have a better name?). It's only
    used when entering/showing estimates now. To define working hours you
    have to use calendars. (The problem with setting calendar for
    resources is also fixes.)
    As you are in calendars, could you implement something like that:
    - a widget to define working day type (where we can say:
    workingDayType1=8:0-12:0, workingDayType2=8:0-12:0 + 14:0-18:0
    )
    - in calendar, use those user-defined day types instead of specifing working
    plages by hand for each
    - multi-selection in calendar to set more than one day at once

    It would be helpfull for those who have partial time working, or are working
    on several project at a time.

    Fixed. BTW, the duration/effort widget, do you you think it works ok?
    Shaheed came up with this since we wanted a (simple) way to localize
    it. It's still kind of prototype, atm it can't handle more than days,
    it should at least handle weeks imo.
    As a project leader, or even as a 'ressource', what I expect is:
    If I have 2 tasks at the same time for a ressource, the duration must take the
    effort into account:
    taskA and taskB are both planned for ressource1 starting at 1rst january and
    both takes 5 days of effort. So, both duration must be 10 days, as
    ressource1 will have to spend 2*5days.
    So, taskA will be:
    - starting at 1/01
    - effort 5days
    - duration 10days
    - ressource usage 50%

    But I must admit that this may be hard to implement, as tasks may overlap at
    random times
    I don't know how other do, but I think it would be very very very usefull!!!

    What is your opinion?

    Fred

    Fred

    Le Mercredi 21 D 2005 14:55, Dag Andersen a *:
    21 december 2005 14:17, fmdp wrote:
    - doesn't handle correctly the task duration when set more than
    one working plage per day (set 13:0->15:0 and 20:0->23:59)=>
    all tasks are displayed as '1 day long' in the gantt

    I don't know what you expected to see , but it should display the
    task as starting 13:0 and ending 23:59. It doesn't show that no
    work is going on from 15:0 to 20:0.

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.9 | | 3284 bytes | |

    Torsdag 05 januar 2006 10:45, fmdp wrote:
    Hi Dag,

    I only updated kplato and it crashes at sometimes.
    so, now, all koffice is updated & compiling and it takes long
    time!!!
    Tip: To run just kplato you need lib, kugar, kdgantt and servicetypes
    (I think).

    few answers to your questions, I'll report success/problems on the
    execution when compilation will be finished (in few hours)

    Le Mercredi 4 Janvier 2006 13:36, Dag Andersen a *:
    , think I fixed it, probably I was interrupted during
    implementation because the functionality wasn't complete. I
    simplified the use of the StandardWorktime thing (do you have a
    better name?). It's only used when entering/showing estimates
    now. To define working hours you have to use calendars. (The
    problem with setting calendar for resources is also fixes.)

    As you are in calendars, could you implement something like that:
    - a widget to define working day type (where we can say:
    workingDayType1=8:0-12:0, workingDayType2=8:0-12:0 + 14:0-18:0
    )
    - in calendar, use those user-defined day types instead of
    specifing working plages by hand for each
    - multi-selection in calendar to set more than one day at once
    I did for weekdays, use ctrl-LMB.
    (Also for weeks actually, but I plan to remove weeks altogether as it
    just complicates things)

    It would be helpfull for those who have partial time working, or
    are working on several project at a time.

    Fixed. BTW, the duration/effort widget, do you you think it works
    ok? Shaheed came up with this since we wanted a (simple) way to
    localize it. It's still kind of prototype, atm it can't handle
    more than days, it should at least handle weeks imo.

    As a project leader, or even as a 'ressource', what I expect is:
    If I have 2 tasks at the same time for a ressource, the duration
    must take the effort into account:
    taskA and taskB are both planned for ressource1 starting at 1rst
    january and both takes 5 days of effort. So, both duration must be
    10 days, as ressource1 will have to spend 2*5days.
    So, taskA will be:
    - starting at 1/01
    - effort 5days
    - duration 10days
    - ressource usage 50%

    But I must admit that this may be hard to implement, as tasks may
    overlap at random times
    I don't know how other do, but I think it would be very very very
    usefull!!!

    What is your opinion?
    I have put off resource leveling till after this release, it's a bit
    much before jan 12 ;)
    Possibly if I have time I may make a simple preliminary solution to
    overbooking, but that's as far as can go for now.

    (PS: You don't have to CC me, I'm on the list :)

    Fred

    Fred

    Le Mercredi 21 D 2005 14:55, Dag Andersen a *:
    21 december 2005 14:17, fmdp wrote:
    - doesn't handle correctly the task duration when set more
    than one working plage per day (set 13:0->15:0 and
    20:0->23:59)=all tasks are displayed as '1 day long' in
    the gantt

    I don't know what you expected to see , but it should display
    the task as starting 13:0 and ending 23:59. It doesn't show
    that no work is going on from 15:0 to 20:0.
  • No.10 | | 2090 bytes | |

    Le Jeudi 5 Janvier 2006 12:26, Dag Andersen a *:
    Tip: To run just kplato you need lib, kugar, kdgantt and servicetypes
    (I think).
    ok, I'll try, it will be faster
    --
    I did for weekdays, use ctrl-LMB.
    (Also for weeks actually, but I plan to remove weeks altogether as it
    just complicates things)
    , it works.
    (personal feeling: I find it hard to see as it is not painted fully in the
    calendar. A manager/ressource may find usefull to have each day really
    painted in bleu/red. It would help to see vacations, overbooked days, )

    What is your opinion?

    I have put off resource leveling till after this release, it's a bit
    much before jan 12 ;)
    Possibly if I have time I may make a simple preliminary solution to
    overbooking, but that's as far as can go for now.
    :)
    I just want to give a 'user' feedback/point of view I hope my suggestions
    do not stress you, that's not the goal!
    I'm too much busy in my own project to invest into kplato code I limit my
    participation to ba a user
    But I know that projects often need 'external feedbacks' I hope mine
    helps

    By the way, a minor bug: in Standard Work Time, if you put 'hours per day' to
    '0.0', it hard-crashes when you modify a task duration:
    fred@joe kplato]$ kplato
    koffice (lib kofficecore): kplatopart.desktop found.
    koffice (lib kofficecore): kplatopart.desktop found.
    koffice (lib kofficecore):
    KoDocument::loadNativeFormat( / )
    kplato: Loading took 0.001 seconds
    kplato: [KMacroCommand*
    (KPlato::Part*)]
    QGDict::hashKeyString: Invalid null key
    kplato: [void (KPlato::Task&,
    KPlato::StandardWorktime*)] daylength=0
    kplato: [void (KPlato::Task&,
    KPlato::StandardWorktime*)] Effort: 1 00:00:00.0
    KCrash: Application 'kplato' crashing

    (PS: You don't have to CC me, I'm on the list :)
    yeap, the traffic is not so heavy to notify you twice! ;)

    Fred

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.11 | | 3039 bytes | |

    Torsdag 05 januar 2006 13:52, fmdp wrote:
    Le Jeudi 5 Janvier 2006 12:26, Dag Andersen a *:
    Tip: To run just kplato you need lib, kugar, kdgantt and
    servicetypes (I think).

    ok, I'll try, it will be faster

    I did for weekdays, use ctrl-LMB.
    (Also for weeks actually, but I plan to remove weeks altogether
    as it just complicates things)

    , it works.
    (personal feeling: I find it hard to see as it is not painted fully
    in the calendar. A manager/ressource may find usefull to have each
    day really painted in bleu/red. It would help to see vacations,
    overbooked days, )
    hmmm, is this the calendar dialog you are talking about? There isn't
    any overbooking info there?
    The reason I didn't use full background color on each day is that you
    can define both weekdays and single day and then you couldn't see if
    you had defined a single day (eg. with different workhours).
    TH I expect the calendar dia to change when we go to KDE4 (in a year
    or so) as I want to use the localized holidays stuff from kde-pim,
    so I haven't put a really serious effort into the calendars (lame
    excuse)

    What is your opinion?

    I have put off resource leveling till after this release, it's a
    bit much before jan 12 ;)
    Possibly if I have time I may make a simple preliminary solution
    to overbooking, but that's as far as can go for now.

    :)

    I just want to give a 'user' feedback/point of view I hope my
    suggestions do not stress you, that's not the goal!
    I'm too much busy in my own project to invest into kplato code I
    limit my participation to ba a user
    But I know that projects often need 'external feedbacks' I hope
    mine helps
    You are very, very wellcome indeed. Exhaustive testing of my own code
    is the hardest thing, and I'm not an extensive user of PMs so there
    are millions of viable ways to use them that I couldn't even dream
    of.
    --
    By the way, a minor bug: in Standard Work Time, if you put 'hours
    per day' to '0.0', it hard-crashes when you modify a task duration:
    Doesn't supprize me, I actually thought of it, but obviously didn't
    test it, thanks.
    fred@joe kplato]$ kplato
    koffice (lib kofficecore): kplatopart.desktop found.
    koffice (lib kofficecore): kplatopart.desktop found.
    koffice (lib kofficecore):
    KoDocument::loadNativeFormat(
    / )
    kplato: Loading took 0.001 seconds
    kplato: [KMacroCommand*
    (KPlato::Part*)]
    QGDict::hashKeyString: Invalid null key
    kplato: [void
    (KPlato::Task&,
    KPlato::StandardWorktime*)] daylength=0
    kplato: [void
    (KPlato::Task&,
    KPlato::StandardWorktime*)] Effort: 1 00:00:00.0
    KCrash: Application 'kplato' crashing

    (PS: You don't have to CC me, I'm on the list :)

    yeap, the traffic is not so heavy to notify you twice! ;)

    Fred

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.12 | | 1784 bytes | |

    Le Jeudi 5 Janvier 2006 14:37, Dag Andersen a *:

    hmmm, is this the calendar dialog you are talking about? There isn't
    any overbooking info there?
    In fact, I was thinking of some code of color related to the amount of work
    for a day: white for 0hour, full-red for 24h/d and a melt between.
    A manager may quickly see periods that are too much red, and try to plan
    quiter days after.
    In little companies, working time is often flexible, but managers have to keep
    in mind that 'ressources' are not slaves! ;)
    So, when I spoke about 'overbooking', it was in fact 'overtiming'

    The reason I didn't use full background color on each day is that you
    can define both weekdays and single day and then you couldn't see if
    you had defined a single day (eg. with different workhours).
    Yeap, I understood that. I was only express my personnal feeling: I prefer to
    see details on a calendar.

    TH I expect the calendar dia to change when we go to KDE4 (in a year
    or so) as I want to use the localized holidays stuff from kde-pim,
    so I haven't put a really serious effort into the calendars (lame
    excuse)
    concentrate on the valuable parts of kplato instead of answer my cosmetic
    remarks! ;)
    So, you are fully right, and I think an interraction with other kde parts are
    very very important (with karm in particular, it would be a must!)
    Forget my color requests for now 8-/

    I let you work in peace from now until the next time!
    oops, last question: is there any place to be aware of commits?
    It would help for testing (detecting problems asap makes correction often
    easier).

    Fred

    kplato mailing list
    kplato (AT) kde (DOT) org
  • No.13 | | 2044 bytes | |

    Torsdag 05 januar 2006 15:45, fmdp wrote:
    Le Jeudi 5 Janvier 2006 14:37, Dag Andersen a *:
    hmmm, is this the calendar dialog you are talking about? There
    isn't any overbooking info there?

    In fact, I was thinking of some code of color related to the amount
    of work for a day: white for 0hour, full-red for 24h/d and a melt
    between. A manager may quickly see periods that are too much red,
    and try to plan quiter days after.
    In little companies, working time is often flexible, but managers
    have to keep in mind that 'ressources' are not slaves! ;)
    So, when I spoke about 'overbooking', it was in fact
    'overtiming'

    The reason I didn't use full background color on each day is that
    you can define both weekdays and single day and then you couldn't
    see if you had defined a single day (eg. with different
    workhours).

    Yeap, I understood that. I was only express my personnal feeling: I
    prefer to see details on a calendar.

    TH I expect the calendar dia to change when we go to KDE4 (in a
    year or so) as I want to use the localized holidays stuff from
    kde-pim, so I haven't put a really serious effort into the
    calendars (lame excuse)

    concentrate on the valuable parts of kplato instead of answer my
    cosmetic remarks! ;)
    So, you are fully right, and I think an interraction with other kde
    parts are very very important (with karm in particular, it would
    be a must!) Forget my color requests for now 8-/
    Yes, and pim and rest of koffice

    I let you work in peace from now until the next time!
    I don't mind you testing, I can always shelf wishes for later :)
    oops, last question: is there any place to be aware of commits?
    It would help for testing (detecting problems asap makes correction
    often easier).
    Yes, kde-commits (AT) kde (DOT) org, see for
    how to filter (else you get all commits for whole kde)

    Fred

    kplato mailing list
    kplato (AT) kde (DOT) org

Re: problem with kplato on current svn version...


max 4000 letters.
Your nickname that display:
In order to stop the spam: 2 + 1 =
QUESTION ON "KDE"

EMSDN.COM